Daily Archives: July 26, 2016

Steps and Stone

Published by:

Renovations

As a continue effort to save some of our crumbling steps we have been applying a non slip sealant to steps in poor or degrading condition.
During the painting and drying process your door mat, plants and decorations may be placed to the side.
The sealant only takes a few hours to dry and owners/tenants may return the items to how you desire once that is done.

We are also going around the complex to repair crumbling or missing stonework on the front of units this should be complete by the end of the year.

Thank you for your time and understanding.

Grading, Drainage and Roadway Update

Published by:

As many of you are well aware we have had some major grading work done around the complex.
We now have accepted a quote from HML Contracting LTD to complete the work that was left unfinished by Do All Landscaping. HML will complete the remaining work as outlined in this post
This work should be complete by the end of 2016.
We have also hired Splashdown Eaves to replace any damaged downspouts around the complex and re route any downspouts as required by the new drainage plan.
Our roadways have developed a few pot holes and sinkage around the complex has resulted in some of the man holes being higher than the lowest points in the road.
We will have Smart Fix Asphalt repairing the various potholes and will be lowering several man holes to fix any drainage problems.

Thank you everyone for your continued patience with the board while these improvements are underway.